- NEPA status
- In Progress - Public Scoping Period (phase label — see periods for the deadline)
- Submissions
- 5 across all periods — refreshed daily
- Program
- Renewable Energy · Solar Energy
- Case file
- NVN-101055
- Lead office
- Pahrump Field Office
- All offices
- Las Vegas FO (FO) · Pahrump FO (FO) · Southern Nevada DO (DO)
- Where
- Nevada — Clark
- Applicant
- Renew Development HoldCo, LLC
- Started
- 7/29/2026
- Updated
- 7/28/2026 5:00:00 PM
What's proposed
Renew Development HoldCo, LLC (Renew Development) has applied to the BLM Pahrump Field Office for a right-of-way grant for authorization to construct, operate, and decommission a 500-megawatt photovoltaic solar electric generating facility, battery energy storage facilities, associated generation tie (gen-tie) line, and access road facilities on approximately 3,565 acres of public lands (Project) located southeast of the town of Pahrump, in Clark and Nye County, 30 miles west of Las Vegas. The electricity generated would be conveyed to the Trout Canyon Substation located east of the project site via a gen-tie transmission line. The Proposed Action also includes an amendment to the Las Vegas RMP to realign designated utility corridors that currently traverse the proposed project area. West-Wide Energy Corridor Segment # 224-225, established under authority of Section 368 of the Energy Policy Act of 2005, traverses the central portion of the project area from east to west. In addition, a BLM Southern Nevada District designated utility corridor, established by the RMP, also traverses the central portion of the project area. Per 43 CFR 1610.5-3, the project must be in conformance with the RMP; therefore, a plan amendment to modify both utility corridors by realigning them outside of the Mosey Solar Project area would be required.
Participation periods
| Period | Closes | Status | Submissions | Comment |
|---|---|---|---|---|
| Mosey Solar Project PP 1 | 2026-08-28 | open | 5 | Participate ↗ |
Contacts
- Jessica Headenjheaden@blm.gov(702) 515-5000
- Whitney Wirthlinwwirthli@blm.gov(702) 515-5117
- Matthew Kleinmklein@blm.gov(702) 515-5025
Milestones
| Milestone | Scheduled | Actual |
|---|---|---|
| draft_eis_publication | 1/15/2027 | 1/15/2027 |
| final_eis_publication | 12/17/2027 | 12/17/2027 |
| notice_of_intent_publication | — | 7/29/2026 |
| record_of_decision_publication | 6/19/2028 | 6/19/2028 |
| start_date | — | 7/29/2026 |
Documents
Check the source:eplanning.blm.gov ↗